Lesson 3 of 9About 6 minutesMegalug steps: lesson 6
1Prep & layout
2Stations
3Tie-in to the city main
4Detector check
5Bed & lay
6Fittings & restraint
7Fire riser
8Cover it right
9Flush & test
Watch
Cut in a tee · from above
The steps
A tie-in is the one part of the job where the city's water is open to the ditch. No pipe gets cut until you have proved the main is dead and stays dead.
The day before: uncover the main. Check its size and what it is made of. On ductile pipe, dig 2 feet clear on both sides and under it, or the saw can't roll all the way around for a full cut. If you have bedding, put some on the trench bottom so you can walk once the water is drained. Take inventory of every part the tie-in needs.
Every part on the truck, counted: tee, fire line valve, a sleeve and pup piece that fit that main, Megalugs, spare gaskets, pump, saw, generator and chlorine.
Before the shutdown, bolt the tee and valve together on the ground. It drops into the hole as one assembly.
Never put a tee within 5 feet of a bell joint. If there is a bell that close, cut it out.
The city shuts it down. The city runs its valves. Our crew can help turn them when the city asks.
Prove a clean kill before you cut anything. Open a drain or hydrant between the valves and watch. The water has to stop and stay stopped.
Still coming? Don't cut. Close it back up and call Rob and the city.
Pump the hole and check the kill again right before the saw touches the pipe. Then mark the main for the tee, pup and sleeve, cut square, and take the piece out.
Clean and swab. Clean the cut ends. On ductile or cast iron, run a descaler over the outside of the pipe where the tee and sleeve go so it is clean metal. Swab the inside of the tee, pup, sleeve and the pipe ends with chlorine the way the city requires.
Drop in the tee and valve, single sleeve. One end of the tee goes straight onto the main. On the other end, a pup piece goes in the tee and one sleeve joins the pup to the main. Branch pointing to the building.
Restrain it the way Fittings & restraint (lesson 6) shows.
The city opens it back up slowly. Watch every joint for leaks before any dirt goes back.
Photo, poly wrap, photo. Take a photo before the poly goes on. Poly wrap the tee, valve, pup and sleeve and tape it closed. Then take a second photo, wrapped.
Your photos
In TJS Field
Two photos of the tie-in, after the city has opened it back up and before any dirt goes on it: one before the poly, one after it is wrapped.
Open TJS Field.
Pick the job.
Tap the camera button, 📷 Take a photo, and take the picture.
Tag it Tap / tie-in.
Photo 1, before the poly
The tee, the pup, the sleeve and the fire line valve
Every breaker head gone
No water at any joint
Photo 2, wrapped
Poly over the tee, valve, pup and sleeve, taped closed