Stations: where you are on the line

Lesson 2 of 9About 5 minutesFor crew and foremen
  1. 1Prep & layout
  2. 2Stations
  3. 3Tie-in to the city main
  4. 4Detector check
  5. 5Bed & lay
  6. 6Fittings & restraint
  7. 7Fire riser
  8. 8Cover it right
  9. 9Flush & test

Watch

The plans and the ground
PLAN VIEW · looking down Tie-inRiser 0+001+002+003+004+005+00 2+44

The steps

A station is how far along the line you are, in feet, from where the plans start it. Every fitting, valve and crossing on the plans has one. Know the station and you know what is coming next, and the next crew and Rob know where you are without driving out to look.

  1. What a station is. The distance along the line from the start. 0+00 is the start. The number before the + is hundreds of feet, so 4+30 is 430 ft along the line.
  2. Decimals. 2+56.4 is 256.4 ft. Some lines start at 10+00 or 1+00: what counts is the difference. 10+00 to 12+50 is 250 ft.
  3. Stations follow the pipe, around every bend, never straight across a turn.
  4. Plan view and profile share the stations. Find the station on the plan view (looking down) for where it is. Go to the same station along the bottom of the profile (looking from the side) for depth, cover and what crosses.
  5. Find where you are from something in the ground at a known station: the tie-in, a bend, a valve, a manhole. Tape along the pipe from it and add. A bend at 2+44 plus 86 ft is 3+30.
  6. The rover shows the station where the pole stands, when the line is loaded in it. Ask Rob.
  7. Put it in TJS Field. End of Day, Installed through station: the farthest station of pipe in the ground today.

Where it goes in TJS Field

In TJS Field

On End of Day, each job with stations on its plans asks Installed through station.

  1. Find the last pipe in the ground today.
  2. Tape back to the nearest thing with a station, or read the rover.
  3. Type it like 3+30.

What it does

  • Moves the crew's marker on the job's line
  • Tomorrow's Start of Day shows what is in the next 100 ft: crossings, fittings, valves
  • Left blank, Start of Day can only guess from the footage

Check

3 questions · get all 3