Any work we had to do twice: a failed test, a joint redone, grade fixed, pipe dug back up. Log it the same day.

Pictures load when you are online.

Why it matters

Do-overs are hours the job was never planned for. Logged, we can see what keeps causing them and fix it. Not logged, they just make the job look slow.

A do-over is not about blame. It is about not paying for the same work twice.

Your turn

In TJS Field

Next time something gets redone: log it that day.

Check

3 questions · get all 3

All the steps

  1. Do-over. On Today, tap ↩ Do-over.
  2. What it was. Pick what it was and who it counts against.
  3. Hours lost. Put the man-hours it cost (men × hours) and a note on why.
  4. Save. Save it.
  5. Not a do-over: waiting. Waiting on the inspector or GC is not a do-over. At End of Day, tap it under What made it hard, and say how long in the one line.