TJS Training · Installing Fire Lines

Bed & lay

Lesson 5 of 9About 5 minutes
  1. 1Prep & layout
  2. 2Stations
  3. 3Tie-in to the city main
  4. 4Detector check
  5. 5Bed & lay
  6. 6Fittings & restraint
  7. 7Fire riser
  8. 8Cover it right
  9. 9Flush & test

Watch

Along the trench, from the side
Grade

The steps

A pipe sits on what you put under it. A good bed and a joint pushed exactly home is a line that holds for fifty years. A short joint, a joint put together at an angle or a rock under the barrel is a leak waiting for the test, or for later.

  1. Dig to depth. Cover on the plans, plus the pipe, plus the bedding. Check it with a tape every stick. Over-dug? Fill it back with bedding and compact it, not loose dirt.
  2. Box and ladder before anyone gets in. A box if it is over 5 ft. A ladder at 4 ft or deeper, within 25 ft of every man in the trench, sticking up 3 ft above the top (OSHA).
  3. Bedding: what the plans say, or 4 to 6 inches under the pipe if they don't. Level, no rocks. Keep the bedding back at least 2 ft either side of the bell, so the pipe sits on its barrel, not its bell.
  4. Look at the stick before it goes in: no cracks, no gouges, gasket seated in the bell.
  5. Lower it in with a strap, not a chain. Never drop it.
  6. Clean and lube. Rag the spigot and the bell, then lube the spigot.
  7. Find the home mark. No mark, or too faded to trust? Make one: measure the bell depth with a tape, measure the same distance back from the spigot end, mark it all the way around. A cut pipe always gets a bevel and a new mark.
  8. Level and square before you push. Bring the spigot to the mouth of the bell level from the side and in line from the top. Cocked either way, it may not seat right.
  9. Home it with a bar until the mark is at the face of the bell: not short, not past. Check it all the way around.
  10. No deflection at the bell. The stick goes into the bell straight and stays straight. Sight down the line before you move on. Check depth with the tape at every joint.
  11. Plug the open end at night.
  12. Photos: the bedding before the pipe goes on it, and the pipe homed.

Your photos

In TJS Field

Two photos on every run.

  1. Open TJS Field.
  2. Pick the job.
  3. Tap the camera button, 📷 Take a photo, and take the picture.
  4. Tag it as below.

Photo 1, tag it Bedding

  • Bedding leveled, before the pipe goes on it

Photo 2, tag it Pipe in trench

  • A joint homed: the mark at the bell
  • The pipe straight into the bell